System Costs
Initial capital costs are similar to those for conventional boiler and chiller systems whilst whole life costs are comparable. However, servicing and maintenance requirements can be negligible.
System costs range from £3,500 to £8,000 depending on the thermal output required and the size of the building to be heated. Typical indicative costs are:
    
Thermal Output (kW)
Building Size (m2)
Total Kit Cost
4
80
£3,477
6
120
£4,209
8
160
£4,509
10
200
£4,871
12
240
£6,933
16
320
£7,583
20
400
£8,065